Project Challenges
3” settlement of a large, heavily reinforced parking garage ramp slab
Design Approach
Utilize EL003 Polymer to compress and densify the subgrade to lift the ramp back to level
Before
Project Support
Worked with the Courtyard Marriott team for facility access and scheduling for minimal interruption to business operations
Results
- Mitigated need to remove and replace the slab
- Within 15 minutes of injections, the slab was ready for use
- Slab was lifted 3” and leveled to original grad