VA Office Slab Lift

Veteran Affairs Building Slab Lift – San Diego, CA

Veteran Affairs Office Building Slab Lift and Foam Jacking

Interior slab lift of building that settled 4 inches

The Veteran Affairs office building in San Diego, CA was experiencing settlement issues with its interior slab. The slab settlement caused separation of the walls from the floor resulting and required a slab lift utilizing our patented polyurethane chemical grout injection process.

Project Challenges

Client:   Veteran Affairs Office Building
Location:   San Diego, CA
The Veteran Affairs office building in San Diego, CA was experiencing settlement issues with its interior slab. After DCP tests were performed in 3 different locations to determine if issues were direclty below the slab or at depth.  The test determined the existence of weak soils at 8 to 16 feet below surface. The building required a slab lift to get the floors back into a useful condition.

In order to deal with the slab settlement, EagleLIFT designed a soil stabilization slab lift approach utilizing a chemical grout injection process that densifies the soil upward.  The process is unique in that it requires no-excavation and a minimal footprint for stabilizing the slab.

Solutions and Results

The chemical grout injection process was performed by injecting the chemical grout at 9′, 12′ and 15′ depths.   The injection pattern stabilized the loose soil layer and increased its weight-bearing capacity.  After the soil layer was stabilized, EagleLIFT conducted the slab lift by injecting directly underneath the slab.

The project was completed in 3 shifts over a weekend with no interruption to the facilities operations. The floor was lifted the full 4 inches and the and the slab was lifted back to original grade. EagleLIFT worked with STSC Engineering to develop a design plan for this slab lift project.]

Our Projects

EagleLIFT Polymer Injection Foundation Lift and Foundation Repair

Port of Oakland Foundation Repair – Oakland, CA

Project Description

Client:   Port of Oakland
Location:   Oakland, CA
Problem Summary: Settlement of gantry crane wheel path of 1/2″ to 4″

Over the years of heavy use, the pavement, base and sub-base beneath the Port of Oakland’s gantry crane wheel paths had started to subside.  Ground subsidence is very common in situations as this, cyclical loading and heavy loading conditions, especially when the loads have increased over the years. The differential settlement not only made it difficult for the operators to align their cargo properly, but also created a safety hazard while the cranes traveled amongst the site. The settlement ranged anywhere from a 1/2″ up to 4″ at the worst case.

Port of Oakland Chooses EagleLIFT

When it comes time for Port Engineers to evaluate the different repair processes for their pavement maintenance and rehabilitation, numerous factors must be considered.  Factors such as down time to the end client, company qualifications, company experience and services being offered.

Once these factors were taken into account, only one contractor met the criteria:  EagleLIFT, Inc.

Approach

Prior to any injections taking place, EagleLIFT conducted a series of Dynamic Cone Penetration (DCP) tests to measure the relative soil density.  The DCP tests indicated that the sub-base needed to be densified at the -2.5′ depth.

The patented Uretek Deep Injection process was then utilized to densify those soils and lift the pavement to grade. The two-part polymer material is injected through 1/2″ tubes which are driven down to depth through the pavement.  The resulting mixture polymerizes beneath the slab, creating minimal heat with optimum expansion.  With this expansion, the material aggressively seeks out voids filling them while densifying surrounding soils and lifting the pavement back to its original elevation eliminating the settlement.

Results

This Port’s proactive approach and willingness to embrace new technology allowed EagleLIFT to work with Port officials and Engineers to address the settlement issues and possible solutions for it. This particular project exhibited the greatest problem to the client since closing the aisles, removing the pavement and replacing it would not only be costly, but also highly disruptive to Port operations.

This patented Uretek method was chosen for the following reasons.  First, laboratory testing of the material used, proved it maintains its integrity for more than 10 years with no shrinkage or degradation.  Recent studies of other one-part grouts found that conventional grouts are significantly impacted by the factor of time and “wet/dry” cycles.  This unique method is quick, eliminates the need for removal and re-pouring as well as dramatically decreasing the disturbance to normal use if this area.  Resins injected cure within 15 minutes allowing full use to be restored almost immediately after the work was completed.

Featured Projects

EagleLIFT Foundation Repair Parking Lot

Home Depot San Francisco Concrete Lifting

7 inch home depot

SAN FRANCISCO CONCRETE LIFTING

Client:   Home Depot
Location:   San Francisco, CA
Problem Summary:  12″ thick 32″x25″ hinge slabs settled more than 7.5″

Home Depot Chooses Patented Polymer Slab Lifting Technique to Lift Sunken Hinge Slabs.

The patented URETEK injection process was chosen by Home Depot to eliminate some settlement / ponding issues of various hinge slabs. These hinge slabs were approximately 32’x 25’ and were more than 12” in thickness. The slabs needed to be lifted an average of 7.5”.

The unique process of the URETEK Method relies on the expansive properties of a two-part expanding resin system (an expansion co-efficient of twenty to one) and a quick cure (15 minute cure time), to lift and re-align while stabilizing weak soils beneath slabs on grade.

LOW COST CONCRETE LIFTING METHODS IN SAN FRANCISCO

The two-part polymer material is injected through 5/8″ inch diameter holes drilled through the slabs. The resulting mixture polymerizes beneath the slab, creating minimal heat with optimum expansion. With this expansion, the material aggressively seeks out voids filling them while densifying surrounding soils and lifting the slab back to its original elevation eliminating the settlement.

This firm’s proactive approach and willingness to embrace new technology allowed Uretek to work with company officials to address the settlement issues and possible solutions for it. This particular project exhibited the greatest problem to the client since re-pouring the slab would not only be costly, but also highly disruptive to daily operations

Solutions and Results

The technicians drilled the 5/8” holes through the slab as a means of delivering the two part polymer to the underside of the slab. Because the material is self-propelled, the polymer expands to gain resistance from soils while aggressively filling voids. Once the voids have been effectively filled and the base soils compressed, the slab begins to lift.

Injections Successful:

EagleLIFT was able to lift 13 back to within 1/8” of their original elevation in approximately 4 shifts. The structural resins reach 90% of their compressive strength within 15 minutes allowing for immediate use of the slab after treatment. The reason for the accuracy is that the URETEK method does NOT depend on the pumping pressure, as some of the conventional methods do, but rather on the expansion rate of the resin. All parties were very pleased with the work done, the short length of time it took to successfully complete the project and the cost savings that resulted from using the URETEK Method.

Featured Projects

san-diego-concrete-lifting1

FOUNDATION REPAIR SAN DIEGO, CA

SAN DIEGO FOUNDATION REPAIR CHALLENGE

san-diego-concrete-lifting118’ linear feet of footing had settled approximately 1/4″ as indicated by the opening between the footing and the poured foundation wall above. Upon further investigation, it became known that the subgrade problem was deeper then originally anticipated. Boreholes showed low soil density values 7’ level. Traditional repairs methods would have been either removing and re-pouring of the foundation or helical piering. Neither of these methods was feasible due to the fact there both are extremely time consuming and the cost would be relatively high. EagleLIFT, Inc. was chosen for a number of reasons such as the 10 yr warranty against any shrinkage or deterioration, virtually no disruption, no added overburden to the already suspect base soils and a project cost that was a fraction of any alternative.

LOW COST FOUNDATION REPAIR METHODS IN SAN DIEGO

EagleLIFT, Inc. placed a series of 7 Deep Injections at the 3’ and 6’ depths beneath the footing spaced at 3’ O/C. We then injected our patented polymer resins, which expand to aggressively void fill and stabilize the weak base soils, in effect creating a series of piles. The expansion nature of the polymer resins create a lifting force of 15 tons/sq.ft., which made the lifting of the footing possible. The expansion of the resins lasts for 3-5 seconds and the material then starts to cure, reaching 90% of its compressive strength within 15 minutes. The photo to the left shows our injection technician injecting the resins through the 1/2″ copper to the required depth.

SAN DIEGO FOUNDATION REPAIR SERVICES

EagleLIFT, Inc. was able to stabilize the entire 18’ length of foundation in one day. The photo to the right illustrates a 3-layrered Deep Injection beneath a foundation to stabilize the structure and densify the soils. The result is a complete void fill and stabilization of the base soils ensuring a solid base for the foundation and loads placed upon it. All parties were very pleased with the work done, the short length of time it took to successfully complete the project and the cost savings that resulted from using the URETEK Method.